Schedule optimization of a large hospital project – 4D BIM starting with the demolition

  • University of Montreal

Research output: Contribution to conference types › Conference Paper › peer-review

5 Citations (Scopus)

Abstract

There are multiple studies emphasising the positive interaction between Lean Construction and BIM use. Nevertheless, it is often difficult to find a direct link between this integrated strategy and the project outcome. This paper presents a case study of a large hospital project in a dense downtown environment, where BIM and Lean were used in synergy - mutually informing each other and catalysing their impact. This project created opportunities for multiple innovations and optimisations. This paper will focus on the positive impact from simultaneously applying 4D-BIM and a variation of takt-time planning to the demolition of the old hospital building adjacent to the new one. The optimization between the demolition and the new construction was crucial for the project, as it allowed the Design-Builder’s company to shorten the schedule by two months and to win the contract. Another innovation was the automated update between master schedule, takt-time plan, BIM model, and project documents (including 2D plans and Virtual Reality). This automated loop makes the schedule available to each construction stakeholder (from client and designers, to the foremen) in the format that is most appropriate and useful for them. It also allows for easy progress tracking and control.

Original languageEnglish
Pages961-972
Number of pages12
DOIs
Publication statusPublished - 2020
Event28th Annual Conference of the International Group for Lean Construction 2020, IGLC 2020 - Berkeley, United States
Duration: 6 Jul 2020 → 10 Jul 2020

Conference

Conference28th Annual Conference of the International Group for Lean Construction 2020, IGLC 2020
Country/TerritoryUnited States
CityBerkeley
Period6/07/20 → 10/07/20

Keywords

  • 4D BIM
  • Demolition
  • Lean construction
  • Mega-hospital project
  • Schedule optimization

ASJC Scopus subject areas

  • Civil and Structural Engineering
  • Building and Construction

Fingerprint

Dive into the research topics of 'Schedule optimization of a large hospital project – 4D BIM starting with the demolition'. These topics are generated from the title and abstract of the publication. Together, they form a unique fingerprint.